The Act 250 District Commission issued a recess memo that outlines all remaining questions and information. We have 30 days to respond. Other parties will have 15 days after our response to offer any comments. The Commission will determine then whether another hearing...

Construction on this project remains on schedule. The Transit Center work is well underway. Work continued on the abutments for the pedestrian bridge. The full schedule:

-Weather tight building - March 22, 2019

-Substantial Completion - August 15, 2019

- Project Completio...