PROJECT DESCRIPTION

A new transit center at One Taylor Street will provide a hub for local bus transportation and 30 new units of housing. Construction is currently underway on the lot behind Capitol Plaza.

LATEST NEWS

Construction on this project remains on schedule. The Transit Center work is well underway. Work continued on the abutments for the pedestrian bridge. The full schedule:

-Weather tight building - March 22, 2019

-Substantial Completion - August 15, 2019

- Project Completion - August 22, 2019